Installation of the conveying system for the baggage handling system at West Cairo Airport

Client: Mechanic LLC

12th of May 2016

Our role in this project was the installation works of the conveying system for the baggage handling system

Soulintec covered mechanical and electrical installation scopes of work. Concerning the mechanical installation we installed the conveying system, aligned all conveyors with laser optics, completed pulling and tracking of all the belts of the conveyors and installed components (photocells, reflectors, switches, end switches and pneumatic switches.

Furthermore during the electrical installation we installed the cable trays, completed the wiring, laying and the termination of cables and we also systemized the cabling system in the system.